Current Works
ESB 3 Way ductline
The works included the construction of an esb trunk line of three 4’’ducts through various surfaces. the job had a few obstacles such as rock and surface water but with the right plant and equipment and the expertise of our workforce we were still able to complete the contract on time and within budget.
Traffic Management Claregalway
LCE were instructed by the client to provide temporary traffic mangement for disconnecting works.
Works included a pre site survey by one of our qualified TTM designers to design a site specific Temporary traffic management plan accompanied by a detailed method statement and risk assesment to assist our trained crew in the safe installation and removal of our TTM equipment.
for this site we chose a conterflow system to limit the disruption to the flow of traffic.
All our workforce are fully trained in the safe installation and removal of TTM.
All our TTM equipment is in accordance to chapter 8 specification.
Aurora Colo Site
The works included clearance of the site which we then built up with 804 stone to the level of the concrete foundation for the colo unit to be set on, the concrete foundation had to bepower floated to leave a smooth finish as it will act as the inner floor of the colo unit, then we completed the base by constructing a concrete walkway around the site and we also supplied and erected chainlink fencing around the hole site for security.
Once the colo unit was lifted in to place we finished off the internal and external tarmcadam reinstatement using 10mm wearing course and a grey 20mm decorative stone
Emergency Works Ballina Co.Mayo
Called out due to 3 collapsed manhole cover on the crossmolina Rd. We provided 3 new manhole covers raised with engineering bricks and m60 rapid setting mortar then reinstated with mastic.
Traffic Management and Road Ironwork Mastic Asphalt Dunmore
LCE were requested by the client to provide traffic management and repair defected ironworks in the carriageway using Mastic Asphalt.
Works included a pre site survey from one of our qualified TTM designers to design a site specific TTM plan accompanied with a detailed method statement and risk assesment to assist our TTM crews with the safe installation and removal of the TTM equipment
We chose a stop/go system on this project so we had more control over the speed of the passing vehicles and there was also an entrance to a housing estate.
All our TTM crews are highly trained in the safe installation and removal of our TTM equipment
All our TTM equipment is in accordance with the chaptert 8 specificationt
All our emergency repair crews are highly trained to safely and efficently complete the projects to the highest of standards.
All materials used are in accordance with the National Roads Authority(NRA)and Transport Infrastructure Ireland(TII) Specifications.
Site by [ Attik Designs ]
Site by [ Attik Designs ]